1.01 DESCRIPTION

This section covers the furnishing and installation of a complete manual sliding door system. It includes track and doors all as required for installation as shown and specified. The General Contractor shall coordinate the work of all trades including the door supplier, hardware supplier, carpenter, mason, and electrician as so specified.

 

1.02 RELATED WORK COVERED BY OTHER APPLICABLE SECTIONS OF SPECIFICATION SHALL INCLUDE:

A. Preparation of Opening
B. Floor Preparation
C. Glass and glazing
D. Caulking

 

1.03 QUALITY ASSURANCE

A.    MANUFACTURER'S QUALIFICATIONS
Provide units produced by a firm with not less than 5 years successful experience in the fabrication of slding doors of the type required for this project.

B. INSTALLER'S QUALIFICATIONS
Engage an installer who is an authorized representative of the door manufacturer for both the installation and maintenance of the type of units required for this project.

1.04 SUBMITTALS

A. PRODUCT DATA
Submit manufacturer's product data and standard details for sliding doors, including fabrication, finishing hardware, accessories, and other components of the work. Include rough-in diagrams, parts lists, and maintenance instructions, as well as certified test data (where required).

B. TEMPLATES AND DIAGRAMS
Furnish templates, diagrams, and other data to fabricators and installers of related work, as needed for coordination of door installation.

C. SHOP DRAWINGS
Submit shop drawings for the fabrication and installation of entrance doors and associated components of the work. Indicate anchors, joint system, expansion provisions, hardware, and other components not included in manufacturer's standard data. Include glazing details (where required).

 

1.05 WARRANTY
Units to be warranted against defect in material and workmanship for a period of one year from the date of installation.

 

 

PART II - PRODUCT

2.01 MANUFACTURER
ICU/CCU sliding door(s) shall be of type(s) and size(s) as indicated on plans, as manufactured by Horton Automatics, a division of the Overhead Door Corporation and as supplied by Eastern Door Service, Inc., Florence, NJ (800) 390-5521.

 

2.02 EQUIPMENT

A. DOOR UNITS
Shall include header and track, jambs, sliding door, threshold and sidelight if required. All structural aluminum sections shall be 6063T-5 alloy not less than .125 inch thickness with safety radius corners on all vertical rails. Continuous extruded header section shall conceal the four, high quality, ball bearing wheels on nylon-covered support track. Concealed guides shall stabilize bottom of door. Anti-derailing means shall be continuous extrusion full length of door travel. Track must be replaceable. An adjustable astragal with double mohair weatherstrip shall be provided on all strike rails. Joining vertical panel rails shall have complementing mohair weatherstripping, while horizontal rails shall be weatherstripped with mohair type fabric. Door panel construction shall be by means of tongue-and-groove key fitted gussets that have two tempered bolts in each corner section to assure against racking failure.

B. FINISH
OPTIONS: All exposed surfaces shall be (Select desired finish)
1) 204-R1 clear anodized aluminum.
2) 313-R1 dark bronze anodized aluminum.
3) Manufacturer's standard powder coat paint finish. Color to be selected by architect from manufacturer's standard color chart.
4) Manufacturer's standard two coat Duranar finish. Color to be selected by architect from manufacturer's standard color chart.
5) Manufacturer's standard three coat Duranar XL finish. Color to be selected by architect from manufacturer's standard XL color chart.
6) Manufacturer's standard exotic Duranar finish. Color to be selected by architect from manufacturer's standard exotic color chart.
7) Special color and finish as indicated (optional)

C. UNIT TYPE
OPTIONS: Units shall be type (Select desired series number)

1) Series 010 (O-X) The sliding panel shall be installed to inside of sidelight. Sliding panel slides along sidelight. (No swing panels in Type 010).

2) Series 0110 (O-SX) The swing-slide panel shall be installed to the exterior of the fixed sidelight. The swing-slide panel(s) (SX) shall swing out 90 degrees from any position of slide movement, and shall be UL listed as an exitway.

3) Series 0310 (SO-SX) The swing out sidelight (SO) shall be installed to the exterior of the swing-slide panel (SX). Swing out sidelight(s) is provided to allow the sliding panel to swing out from any point of slide travel.

 

 

PART III - EXECUTION

3.01 INSPECTION
Installer must examine the areas and conditions under which doors are to be installed and notify the Contractor in writing of conditions detrimental to the proper and timely completion of work. Do not proceed with the work until all unsatisfactory conditions have been corrected in a manner acceptable to the installer and in accordance with approved shop drawings.

 

3.02 INSTALLATION
Comply with specifications and recommendations. Set track and operator plumb, level and true to line, without warp or rack of doors. Anchor securely in place. Isolate aluminum and other corrodible materials from sources of electrolytic action at points of contact. Install complete door operator system in accordance with manufacturer's instructions, including drive mechanism, controls, and control switches.

 

3.03 ADJUST AND CLEAN
Adjust operator and controls for optimum condition and safety. Lubricate operating equipment. Clean surfaces promptly after installation, exercising care to avoid damage of the protective coating (if any). Advise contractor of protective treatment and other precautions required through the remainder of the construction period, to ensure that doors will be without damage or deterioration (other than normal weathering) at the time of acceptance.

END OF SECTION

| Home |    | Site Map |    | Contact Us |
| Products |    | Manufacturers |    | Services |    | Information |
| Privacy Policy |    | Terms of Use |
| Fun Stuff |    | Links |
| Jobs at EDS |

Page last updated
by Charles F. Vetter

Saturday, June 19, 2004